Need to view external link summary (cross project dependencies) RRS feed

  • Question

  • I have a master schedule that has multiple cross project dependencies (linked across multiple sub-projects).  When I open the master schedule (MPP file) I have typically seen the following pop up (external link summary): 

    However, after completing a set of updates recently, I no longer see the pop up. But the dependency links are still present (appear as ghost line items) in the master schedule. 

    Without that pop up (external link summary), I will have no idea of which of the links are broken and need to be fixed. 

    Thanks for any feedback. 

    Saturday, November 7, 2015 1:17 AM

All replies

  • Bomasamudram --

    Click the Project tab to display the Project ribbon, and then click the Links Between Projects button in the Properties section of the ribbon.  That should display the dialog you want to see.  Hope this helps.


    Dale A. Howard [MVP]

    Saturday, November 7, 2015 9:55 PM