Project Server 2007/2010 - RBS field update RRS feed

  • Question

  • Hi, we are updating RBS structure manually. Is there a way to automate it? In which database/table RBS data is stored? Could we update it manually? Thanks.
    Sanjeev
    Monday, September 12, 2011 5:41 PM

All replies

  • Updating the entire structure automatically sounds a bit difficult - as it
    may have a lot of unintended consequences.
     
    Easiest thing would be to open all resources periodically in MS Project,
    then script a VBA macro to update everyone's RBS (or just copy from Excel)
    per some sort of common record.
     
     

    Andrew Lavinsky [MVP] Blog: http://azlav.umtblog.com Twitter: @alavinsky
    Monday, September 12, 2011 7:24 PM