none
How do I know whether an Actual Work has been filled up through Timesheet by the Resource or directly in Project Pro by the Project Manager? RRS feed

  • Question

  • Hi,

    I'm using Project Server 2010.

    I'm using Single Entry Mode, but allowing the PM's to enter Actual Work through Project Professional, this is because they need to enter the progress of some tasks that are assigned to Generic Resources.

    I would like to make an SQL Script able to inform me about the Actual Work, or %Complete, that had been entered directly in Project Professional by the Project Managers, so that I will be able to track whether a Resource Timesheet has been overwritten by mistake.

    Do you know if it is possible to track this information?

    Thank you for your help and Happy New Year!!

    Regards,

    José Espases

    Thursday, January 3, 2013 11:53 AM

Answers

All replies