finish variance does not display RRS feed

  • Question

  • We work with project server 2010 and Microsoft project 2010.I have an issue.I publish a project on the server successfully. The day after that, the finish variance of some tasks have been disappeared. I have tried re-planning and republishing the project and every single finish variance is displayed but after a day or two the problem shows again. The problem is really bothering.

    I would be grateful if anybody could help me.


    • Edited by SepidehGh Monday, May 23, 2016 6:48 AM
    Saturday, May 21, 2016 8:32 AM

All replies

  • Did you baseline your project after finalizing the plan? For variances to be displayed you need to have baseline values. variances are always calculated from baseline to current values..

    Regards,

    Faizan.


    Regards, Syed Faizan ur Rehman, CBPM®,PRINCE2®, MCTS