Copy Paste issues in MS Project 2013 in time phased part of a view RRS feed

  • Question

  • Hello,

    I cannot paste values (work, cost) in the timphased part of the "task usage" or "resource usage" views. Has somebody encountered this problem, and if so has somebody found a solution?

    Regards
    Wim


    Version info: MS Project Professional 2013 (15.0.4433.1506) MSO (15.0.4535.1002) 32-bit
    Monday, October 14, 2013 10:23 PM

All replies

  • Timephased values can't be pasted. the only way to copy timephased values into Project is with VBA using the TimescaleData method.

    Rod Gill

    The one and only Project VBA Book

    Rod Gill Project Management

    Tuesday, October 15, 2013 5:30 AM
    Moderator
  • Hi,

    In Previous versions, it was possible... :(

    I was trying to do my budgetting excercise via the use of budget resources. Since I have 12 cost budget resources and a time granularity of a month( 12 in a year), this becomes hell of a job!

    In previous versions of MSP this was working perfectly

    Regards
    Wim

    Tuesday, October 15, 2013 12:17 PM