PS2010: How to keep permissions on a project and its pwa workspace in synch ? RRS feed

  • Question

  • Hi,

    I am using Sharepoint 2010 together with Project Server 2010. I have created a couple of projects and their corresponding project workspaces.

    How can I get the permissions on the projects in synch with the permissions set on their assigned project workspace ?

    Are they completely separate?

    Example:
    I would like the PM to have administrative/contribute access to the project workspace.
    I would like a team member/resource to have atleast read or contribute access.

    Thanks for help!

    Sven

    Wednesday, August 31, 2011 11:22 AM

Answers

  • OK, I did some research and found out that there is some kind of built in synch mechanism. In regards to the permissions a user has on Project Server, Sharepoint will set the permissions on the Project Workspaces.

    By default there are these permission levels:

    • Web Administrators (Microsoft Office Project Server)
    • Project Managers (Microsoft Office Project Server)
    • Team Members (Microsoft Office Project Server)
    • Readers (Microsoft Office Project Server)

    For reference see this URL

    http://technet.microsoft.com/en-us/library/cc197668.aspx

     

    • Marked as answer by Sven W Wednesday, August 31, 2011 5:01 PM
    Wednesday, August 31, 2011 1:40 PM
  • Hi Sven,

    Project workspace permission works based on the project member role in project, When a user is a member of the Project Team, they get read permissions, when they are assigned to a task in the project, they get contribute rights.    so i believe this automatically resolves your requirement you mentioned, hope this helps.


    | Khurram Jamshed | Follow my blog about Enterprise Project Management Solution | http://khurramjamshed.blogspot.com |
    • Marked as answer by Sven W Wednesday, August 31, 2011 5:01 PM
    Wednesday, August 31, 2011 4:53 PM

All replies

  • OK, I did some research and found out that there is some kind of built in synch mechanism. In regards to the permissions a user has on Project Server, Sharepoint will set the permissions on the Project Workspaces.

    By default there are these permission levels:

    • Web Administrators (Microsoft Office Project Server)
    • Project Managers (Microsoft Office Project Server)
    • Team Members (Microsoft Office Project Server)
    • Readers (Microsoft Office Project Server)

    For reference see this URL

    http://technet.microsoft.com/en-us/library/cc197668.aspx

     

    • Marked as answer by Sven W Wednesday, August 31, 2011 5:01 PM
    Wednesday, August 31, 2011 1:40 PM
  • Hi Sven,

    Project workspace permission works based on the project member role in project, When a user is a member of the Project Team, they get read permissions, when they are assigned to a task in the project, they get contribute rights.    so i believe this automatically resolves your requirement you mentioned, hope this helps.


    | Khurram Jamshed | Follow my blog about Enterprise Project Management Solution | http://khurramjamshed.blogspot.com |
    • Marked as answer by Sven W Wednesday, August 31, 2011 5:01 PM
    Wednesday, August 31, 2011 4:53 PM
  • Hi,

    yes you are right. That's what I found out in the Technet article aswell.

    Regards

    Sven

    Wednesday, August 31, 2011 5:02 PM