Cost resources and calendar (PWA 2013) RRS feed

  • Question

  • Hello,

    Why, in PWA 2013 (on premises) Cost resources have a Base calendar?

    Thanks


    • Edited by WLID1966 Saturday, January 17, 2015 2:44 PM
    Saturday, January 17, 2015 12:08 PM

Answers

  • Although it is not logical that a cost resource has a base calendar, the logic is anyway respected since the cost resource does not obey to the calendar. Have you tried to open it in MS Project Pro to see if you can also change the base calendar of a cost resource?

    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    • Marked as answer by WLID1966 Sunday, February 1, 2015 3:51 PM
    Wednesday, January 28, 2015 7:02 PM
    Moderator

All replies

  • Hi WLID1966,

    I cannot test it right now so can you give more détails? Are you in Project Pro or in PWA/manage users? At least with Project 2010, the base calendar field was not available for cost resources. A screenshot would be appreciated.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Wednesday, January 28, 2015 2:05 PM
    Moderator
  • Hi,

    I'm in PWA 2013 : Resource Center. I inserted the Base Calendar field and I was surprised to see that Cost Resources has a base calendar: standard. I can change it, but in fact these cost resources don't obey there calendar.

    Wednesday, January 28, 2015 5:10 PM
  • Although it is not logical that a cost resource has a base calendar, the logic is anyway respected since the cost resource does not obey to the calendar. Have you tried to open it in MS Project Pro to see if you can also change the base calendar of a cost resource?

    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    • Marked as answer by WLID1966 Sunday, February 1, 2015 3:51 PM
    Wednesday, January 28, 2015 7:02 PM
    Moderator
  • Guillaume,

    Project Pro doesn't  display any calendar for cost resources

    Thanks