  • We use project server 2013 and I would like to set up a view that shows 'slipped tasks', i.e. all tasks who finish date is after the deadline date.

    How do I do this as it doesn't seem possible to compare two fields in a filter?

    Tuesday, September 19, 2017 12:16 PM

All replies

  • Ness --

    First of all, when the Finish date of a task slips past its Deadline date, Microsoft Project will display a red diamond in the Indicators column.  If you have a large project and want to filter for this condition, the filter criteria would be:

              Deadline          Does not equal          NA

    And     Deadline          Is less than               [Finish]

    I created and tested this filter and it does work.  I created it by making a copy of the Tasks with Deadlines filter, and then modifying the copy.  Hope this helps.


    Dale A. Howard [MVP]

    Tuesday, September 19, 2017 1:47 PM
    Moderator
  • Hi

    I'd like that exact deadline indicator in a .project server view please. It isn't possible, in PWA, to filter one field (finish) against another(deadline). Or is it possible?

    Tuesday, September 19, 2017 3:00 PM
  • Hi HFprojects,

    Sorry to jump in here, but it is not possible.  As a work around, you could use a flag field called "Deadline Exceeded" with the formula iif ( [Finish] > [Deadline], 1, 0) .  Then in a new/modifled PWA project view you can filter where Deadline Exceeded = Yes.  

    Just tried it and it works a treat.


    Ben Howard [MVP] | web | blog | book

    Tuesday, September 19, 2017 4:52 PM
    Moderator
  • Hi Ben

    That is an excellent solution but I was not able to use it the way I need it.

    I need to use that custom field that refers to [Deadline] and this is not possible in the Resource Entity. That means I can show the tasks of the resource, but how can I show if they have slipped?






    • Edited by HFprojects Monday, September 25, 2017 9:44 AM