    Do the approved Resource Engagements for committed resources reflect in the capacity planning graphs: remaining availability, work by resource, resource utilization, resource utilization by project?

    My client currently uses Project Server 2013 and the users are comfortable using Resource Plans (with generic resources) to highlight resource needs, demand, capacity, etc. Once a resource plan is created it updates all the resource graphs without having the PM's do task level assignment. How best can this be replicated in PS2016?

    Thanks for your help