  • Hey guys,

    I've been struggling with MSP in all past versions to uderstand the field "% Work Completed". I assume it should show the difference in duration completed and work completed (I could have 20% duration, but already 50% work done)..

    Anyway - if I try to manually enter 20% duration completed and then 50% work completed, nothing happens :( It should automatically raise the actual work field but it doesn't..

    So guys, can you tell me if the value "% work completed" is actually used somewhere else than just in this field? I couldn't figure it out :/

    Thanks, Milan