none
Approval Center Error: One or more categories of approval could not be loaded RRS feed

  • Question

  • Hi Team,

    We are using EPM 2013 version , recently one of our user encountered a problem with Approval Center while accepting task updates, on the Default welcome page he has 112 Pending approvals but while clicking Approval center he getting error as "Error: One or more categories of approval could not be loaded when user wants to approve" We have checked on the following possibilites but still we are facing this issue Kindly help us on this

    1. I have checked user permission He has Project Manager Access and Timehseet Approval Access

    2.While changing the task ownership to another PM and the task is reflecting correcly on the new PM's Approval center while reverting back the task owneership he faces same issue.

    3. He is trying  for the task updates, we have tried re sving user profiles but nothing changed issue still occours

    4. Checked on the ULS Log And find the error

    Permission denied: User i:0#.w|enterprise\User01

    does not have global permission 'ManageServerConfiguration'.

     Please revert for any other information required.

    Thank you

    Senthil Gopi


    Thanks and Regards, Senthil Gopi

    Wednesday, December 24, 2014 9:38 AM

All replies