Exchange 2010 Database Backup from DPM 2012 R2 RRS feed

  • Question

  • Hi Team,

    My colleague had Configured Exchange 2010 Database backup in DPM 2010 that was working fine both full and incremental.

    Now i have implemented the new DPM 2012 R2 and Create the Protection Group of same Exchange server 2010 DAG, In which I have selected all the DAG Members (Active and Passive) with Weekly full and incremental on every 24hrs...

    I am using Disk Backup in earlier as well as currently with DPM 2012 R2..

    full backup is fine but some times incremental is fine and some times i am getting below error while incremental backups only..

    Once i tried to create the manual recovery of Incremetal backup also getting the same error some times and worked sometimes.

    i have followed many articles but as of now issue is same . please suggest for solution.. Also I have below query...

    1. While Creating the Protection Group, in DAG which DAG Member or DB (Active or Passive) copy should I choose  for the backup?

    2. Is all the Active and Passive Exchange DB Backup required from DPM ?

    3. steps to recover any Mailbox from DPM Disk Disk Backup , please share any Articles for that..

    Error that i am getting during Incremental Backup

    DPM has detected a discontinuity in the log chain for Exchange Mailbox Database on ServerName since the last synchronization. (ID 30216 Details: Unspecified error (0x80004005))”

     


    Shailendra Dev