Added tasks do not report correctly RRS feed

  • Question

  • We have several PMs using MS Project. Many of these PM's modify schedules by adding tasks of modifying task durations or start finish dates after assigning a percentage complete. I have found that many of these schedules will not report correctly or project will not include them in the critical path although they should be included. many times, the problem has been resolved by hand jamming a new project file and deleting the old.  (Project files are baselined)

    I would like to know how to "repair" these broken project files without having to re-create the entire project.

    Tommy

    Tuesday, February 27, 2018 12:36 PM