Sub tasks not showing RRS feed

  • Question

  • I have received schedule, but when I open it only the top level summary shows.  I have used the outline tab on the view menu, but nothing shows at any level am I missing something?
    Friday, November 22, 2019 12:25 AM

All replies

  • Hi BudScud,

    If you have already clicked on "All SubTasks" under the outline, and still not able to see all the tasks then there might be a filter applied for "Summary Tasks".

    Just select "No filter/Clear Filter" from the Filter which is just beside to the Outline button under the "View" menu.


    Rajkumar Allepu (MCP) , | https://sharepointprojectserver.com ** Please mark it as answer if my answer would resolved your issue.

    Friday, November 22, 2019 5:05 AM
  • In addition to Rajkumar's excellent response, a filter might not be displayed in the Filter UI if a filter has been applied using the AutoFilter dropdown from a column header.   A quick way to remove filters is to press F3 which clears all applied filters.


    Ben Howard [MVP] | web | blog | book | downloads | P2O

    Friday, November 22, 2019 8:45 AM