How can I correct, if create Timesheet period incorrectly? RRS feed

  • Question

  • I misdunderstood and creat the first day of 2015 calendar as 1 Jan 2015, inspite of Monday 5 Jan. This will impact to the remainig period because it will show this error

    "Project Web App time reporting periods cannot have duplicate names, gaps or overlaps between adjoining period start and end dates. Period "New Period :12/24/2015-12/30/2015" does not conform to the period naming standard. Correct the periods, and then save your data again."

    Pls. help & thanks in adv.

    chariya I.

    Tuesday, March 17, 2015 4:23 AM

All replies

  • Hi Chariya,

    If the users have not entered any data then you can delete the timesheet periods and then recreate them. If the users already entered some data, then you can delete all future periods (e.g. 19th March onwards) and recreate the periods using the correct settings. In this case the first reporting period you will create will be 19 - 22 March and then you can create the other ones in bulk

    Hope this helps

    Paul