none
Project 2007 filters RRS feed

  • Question

  • We have a standard view set up in our ent global that uses a filter.  Some Projects have blank lines between phases the project schedule. When using the filter the blank lines are hidden,  is there any way to show blank lines in between tasks when using a filter?

    Friday, June 29, 2012 12:52 PM

All replies

  • No. Such blank lines are not really 'tasks'. they are 'null' lines so there is not a good way to filter them since Project doesnt see them as filterable entities.


    Brian Kennemer - Project MVP
    DeltaBahn Senior Architect
    endlessly obsessing about Project Server…so that you don’t have to.
    Blog | Twitter | LinkedIn

    Friday, June 29, 2012 4:02 PM
    Moderator
  • Thats what I expexted.  Thanks for your reply.

    Friday, June 29, 2012 5:33 PM