Entering in 75% Complete but MS Project (2010) is changing it to 100% RRS feed

  • Question

  • This is only happening to some tasks not all.  If I lower the % Complete to 50 then MS Project accepts that.  Do you know how to fix this?

    Thanks!!

    Thursday, November 6, 2014 12:03 AM

Answers

  • Hi,

    It depends on how you've allocated your resources, task types etc.

    I have put together an example and when I enter 50% the task is marked as completed

    The task type is Fixed duration in my case

    and when I enter 25% everything is fine. As soon as I try 50% or 75% the task is marked as completed.

    The reason for that is that my resource works only the first 2 days on this task

    Hope this helps

    Paul

    Thursday, November 6, 2014 11:02 AM

All replies

  • Hi,

    Is it happening on a single project? In case it is, it might be corrupted. To repair it, try the XML export or the save for sharing method.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Thursday, November 6, 2014 3:27 AM
    Moderator
  • This is a tough one. If your plan is not corrupt as Guillaume suggest, then we would need to know a lot more about the schedule and your methods. There is always a logical explanation for these things when corruption is not the answer.

    Gary Chefetz, MCITP, MCP, MVP msProjectExperts
    Project and Project ServerFAQs
    Project Server Help BLOG

    Thursday, November 6, 2014 10:49 AM
    Moderator
  • Hi,

    It depends on how you've allocated your resources, task types etc.

    I have put together an example and when I enter 50% the task is marked as completed

    The task type is Fixed duration in my case

    and when I enter 25% everything is fine. As soon as I try 50% or 75% the task is marked as completed.

    The reason for that is that my resource works only the first 2 days on this task

    Hope this helps

    Paul

    Thursday, November 6, 2014 11:02 AM