none
How can i get some information from another pwa RRS feed

  • Question

  •  Hi all

        here is my problem:

    i have two PWA site (PWA1, PWA2),  When publish project in PWA1 site, i want get some information (such as task, milestone, etc) from another (PWA2), and add them to the publishing project .  now, i do it use event handler (OnPublishing),  call QueueAddToProject method to add the information, but it fails. the job status always Processing until i cancel the job, and there is no error message show. 

        can any one help me? or have the other way to do it ?

    Monday, December 17, 2012 9:16 AM

All replies

  • I cannot say why you are maintaining two PWA sites, as one is enough for any big organization.

    And you are asking PSI development question in the project server general question answer forum, please post this question to the http://social.technet.microsoft.com/Forums/en-US/project2010custprog/threads forum for better responce from the experts.

    By the way you need to double check your code (.cs) file, pull your task information through store it in any class or dictionary then push it in the project in which you are publishing, if your code is getting fire in between workflow process or in checked-out, you need to use the existing checked out session, read the checked out session GUID from publish datasource enum.

    Regards,


    Avinash kumar | Blog:http://avigr8.wordpress.com

    Saturday, December 29, 2012 5:54 PM