  • I am working in a sandbox environment to sample the "out of the box" functionality of project server 2010.  we are currently using a VERY customized 2007 version.

    Questions: 

    1. is there a way to make the task data wrap automatically on a global level so you can read the entire task without having to expand the cell?

    2.  can the column data be changed?  i would want them in a different order and add a couple fields.

    Tuesday, February 5, 2013 4:51 PM

Answers

  • Debbie --
     
    To answer your questions:
     
    1.  No, there is no way to make task names wrap globally on the Timesheet or Tasks page in PWA.
     
    2.  Yes, you have a limited amount of control over the columns displayed in the Timesheet by editing the Timesheet view in PWA.  Click Server Settings > Manage Views.  You can edit the columns and their order in either the My Timesheet view and/or the My Work view.  Be forewarned that you can not have as much control over the order of the columns as you would like
     
    Hope this helps.
     

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Tuesday, February 5, 2013 5:39 PM
    Moderator

All replies

  • Debbie --
     
    To answer your questions:
     
    1.  No, there is no way to make task names wrap globally on the Timesheet or Tasks page in PWA.
     
    2.  Yes, you have a limited amount of control over the columns displayed in the Timesheet by editing the Timesheet view in PWA.  Click Server Settings > Manage Views.  You can edit the columns and their order in either the My Timesheet view and/or the My Work view.  Be forewarned that you can not have as much control over the order of the columns as you would like
     
    Hope this helps.
     

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Tuesday, February 5, 2013 5:39 PM
    Moderator
  • Debbie,

    1. Unfortunately timesheet page can not be customized other than available out of the box options.

    2. Yes, From PWA >> Server Settings >> Manage Views, edit My timesheet or My Work view to re-organize the column


    Hrishi Deshpande – Senior Consultant DeltaBahn
    Blog | < | LinkedIn

    Please click Mark As Answer; if a post solves your problem or Vote As Helpful if a post has been useful to you.This can be beneficial to other community members reading the thread.

    Wednesday, February 6, 2013 3:13 PM
    Moderator
  • thank you for answering...wish you #1 would have been a "yes and heres how you do it.." :)
    Thursday, February 7, 2013 6:16 PM
  • thank you for your help!! :)
    Thursday, February 7, 2013 6:16 PM
  • You are welcome.

    Hrishi Deshpande – Senior Consultant DeltaBahn
    Blog | < | LinkedIn

    Please click Mark As Answer; if a post solves your problem or Vote As Helpful if a post has been useful to you.This can be beneficial to other community members reading the thread.

    Thursday, February 7, 2013 6:19 PM
    Moderator
  • Debbie --
     
    You are more than welcome for the help, my friend!  :)

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Thursday, February 7, 2013 6:36 PM
    Moderator