none
Timeline in Project Pro 2016 RRS feed

  • Question

  • Hi,

    I created a new timeline in Project 2016 and I expected to set a different date range, but the Date Range button is grayed out.

    What did I miss?

    Thanks 

    Saturday, October 3, 2015 2:47 PM

Answers

  • Hi,

    You have to select one of your timeline first, then the date range button should become active. You can set a date range per timeline.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, MCC |

    • Marked as answer by WLID1966 Thursday, October 8, 2015 11:53 AM
    Sunday, October 4, 2015 8:55 PM
    Moderator