  • Project 2007.

    Is there a "quick" way to mark a task complete, versus opening the task and changing "percent complete" to 100%?
    Something like a keyboard shortcut, etc.

    Thanks.

    Friday, June 17, 2011 1:32 PM

Answers

  • Never mind, I found my answer in another forum.

    Turn on the Tracking toolbar (Select View, Toolbars, Tracking). There are buttons on that toolbar to mark a task as 25%, 50%, 75%, and 100% complete with a single click. Just pick the task you want to set and click the appropriate button.