Error on save RRS feed

  • Question

  • I was trying to save some updates on a schedule to the server and got the the following error message:  Job Type:  "Save",  Error ID:  "9000(0x2328)."   I imported this project using the import wizard.  Any ideas on what causes this?

    Tuesday, January 4, 2011 4:05 PM

Answers

All replies

  • you would find more appropriate error description in ULS Log, if you could share that we would be able to suggest 
    Thanks | Sunil Kr Singh | http://epmxperts.wordpress.com
    Tuesday, January 4, 2011 5:25 PM
    Moderator
  • We are experiencing same issue, and unfortunately it happens quite often.

    Here are some details from ULS logs that I could find:

    PWA:http://project/PWA, ServiceApp:Project Server Service Application, User:xxxx, PSI: [T:03ad14b0-4909-43b8-b7cb-e86da19476ae][U:08760db3-b1fc-41b3-b003-787b624583e8][S:987c4018-742c-42de-97c9-bcc393c5541b][D:TML1439\2010 Production][J:03ad14b0-4909-43b8-b7cb-e86da19476ae][P:f42e1e6a-28b3-4c52-a503-c2e90a71a6e3][PS_AC][1] Enter PreSaveProject(f42e1e6a-28b3-4c52-a503-c2e90a71a6e3, 0, True, 987c4018-742c-42de-97c9-bcc393c5541b, TML1439\2010 Production, True, True, 03ad14b0-4909-43b8-b7cb-e86da19476ae)

    PWA:http://project/PWA, ServiceApp:Project Server Service Application, User:\xxx, PSI: [T:03ad14b0-4909-43b8-b7cb-e86da19476ae][U:08760db3-b1fc-41b3-b003-787b624583e8][S:987c4018-742c-42de-97c9-bcc393c5541b][D:TML1439\2010 Production][J:03ad14b0-4909-43b8-b7cb-e86da19476ae][P:f42e1e6a-28b3-4c52-a503-c2e90a71a6e3][PS_AC][2] Cancelling correlation f42e1e6a-28b3-4c52-a503-c2e90a71a6e3 as save is an overwrite or resubmit.

    PWA:http://project/PWA, ServiceApp:Project Server Service Application, User:, PSI: [QUEUE] [PSI] CancelCorrelation(f42e1e6a-28b3-4c52-a503-c2e90a71a6e3,True)

    Any ideas what could be causing this?

    We are running project server 2011 with October CU installed

    Thursday, February 10, 2011 1:09 AM
  • These types of problems are most often related to the quality of the data in the schedules. Do you have blank lines in these schedules? Do you have any blank summary tasks? Inasmuch as this thread has been idle for a while, I'm going to close it for now.
    Gary Chefetz, MCITP, MCP, MVP msProjectExperts
    Project and Project ServerFAQs
    Project Server Help BLOG
    Sunday, February 27, 2011 2:43 PM