  • Question

  • I have 10 projects and have created a consolidated project with each project as a subproject.  Have also created a resource pool.  I'm trying to create a report that shows each resource and the milestone that they will be working on during each week of the project.  I can get reports by resource at a task level but not by date at a milestone level.  Any ideas .  Thanks

    Thursday, February 28, 2013 9:35 PM

All replies

  • Hello Libertybend,

    If I'm getting this right, you need to show when a resource would finish his/her work. You can achieve this by using "Finish date". You should not assign resources to a milestone.

    Best regards,


    Rene Alvarez

    Friday, March 1, 2013 1:16 AM