none
update local project calendar with enterprise calandar RRS feed

  • Question

  • Hi,

    I have a project with local project calendar, like "Local_Calendar" with sat, Sunday nonworking document. where i have to sat Friday nonworking hours and make sat, sun working hours. for that i have created enterprise calendar where i have mentioned Friday non working item and sat, Sunday working hours.

    now problem is that when i change/update my project calendar from "Local_Calendar" to Enterprise calendar than it reflect only on new task, after update if i create new task and select Friday its prompt message Friday in non working.

    in already created task, where task assigned on Friday now Friday is non-working so how can i update dates, i tried to change but its now allowing.

    pls guide how can i make reflection of calendar changes to already assigned dates. how can i make task fit according to new calendar.

    Thx



    iffi

    Wednesday, July 4, 2018 10:48 AM