none
DPM 2012 became evaluation copy after update RRS feed

  • Question

  • Hello Support,

    We've been using System Center 2012 - Data Protection Manager for quite some time.

    We checked update and downloaded System Center 2012 SP1 for DPM. After installing & using for a while, we noticed that it prompted us for expiry soon. My question is that we have a valid copy of System Center 2012 for DPM, why suddendly it became evaluation copy? And how can we make it valid and not to expire?

    Best Regards,

    Christy

    Thursday, July 2, 2015 3:44 AM

Answers

  • Hi,

    DPM 2012 Sp1 is a complete SKU not just a service pack, so you need to enter a valid product key.  It sounds like you downloaded the evaluation of DPM 2012 SP1 and now you need to upgrade it to the full retail version and supply a valid product key during that upgrade.  That should remove the time bomb.


    Please remember to click “Mark as Answer” on the post that helps you, and to click “Unmark as Answer” if a marked post does not actually answer your question. This can be beneficial to other community members reading the thread. Regards, Mike J. [MSFT] This posting is provided "AS IS" with no warranties, and confers no rights.

    Monday, July 6, 2015 3:55 AM
    Moderator