Locked tasks feature in reporting RRS feed

  • Question

  • Hi Experts!!

    The 'Close Tasks to Update' feature which is renamed as 'Locked' in Project 2013, how can I extract a report of all locked tasks across Projects in Project Online using ODATA feed??

    TIA


    Manish

    Monday, April 18, 2016 7:38 AM

Answers

  • Hi All

    I have created a formula custom field at task level which refers to 'Locked Tasks' field and hence have same value as in 'Locked Tasks' field, and now this new custom field can be fetched in reporting.

    Thanks.


    Manish

    Wednesday, May 18, 2016 9:54 AM

All replies

  • manish,

    the feed you need to be looking at is the Assignments feed, and I beleive that the field you need is the "AssignmentisPublished", which is set to true or false.


    Cheers,

    Prasanna Adavi, Project MVP

    Blog:   Podcast:    Twitter:    LinkedIn:   

    Monday, April 18, 2016 1:54 PM
    Moderator
  • Hi Prasanna

    Thank you for your reply.

    But this field does not help me in finding those tasks which are locked for update by Team Members.


    Manish

    Tuesday, April 19, 2016 4:51 PM
  • Hi All

    I have created a formula custom field at task level which refers to 'Locked Tasks' field and hence have same value as in 'Locked Tasks' field, and now this new custom field can be fetched in reporting.

    Thanks.


    Manish

    Wednesday, May 18, 2016 9:54 AM