  • Hi,

     

    I am trying to run the earned value report from the "visual reports". I choose to calculate by month. the result shown for 1 month only (I am expecting to see a line whith earned value calculeted for each month from the beginning of the project till the end)

     

    what I am doing wrong?

     

    Thanks,

    Hanni


    Hanni, PMO
    Monday, December 12, 2011 3:18 PM

Answers

All replies

  • Hi Hanni,

    First to deal with the basics - do you have SP-1 installed?

    Are all of your tasks expanded to the lowest level when you attempt to run the report?

    I am guessing that you see earned value data in the timescaled portion of the Task Usage or Resource Usage view?

    Julie

    Monday, December 12, 2011 5:04 PM
    Moderator
  • Also, in the excel file, did you select "Time Monthly Calendar" in the pivot table field list?
    Monday, December 12, 2011 5:06 PM
    Moderator
  • Hi,

     

    Thanks for your answer. I played a bit with the "time monthly calendar" in the pivot and it is OK now.

     

    Hanni


    Hanni, PMO
    Monday, December 12, 2011 6:30 PM
  • Great.  I'm glad you've been able to work it out using the "time monthly calendar" setting.