  • Hi,

    In Project Online 2013 we are able to create several calendars, but where in the Project Online interface, can we attache a calendar to a resource?

    Thanks

    Tuesday, August 6, 2013 1:31 PM

Answers

  • Hello,

    This works the same way as on-premise. Edit the enterprise resource in PWA > Resource Center, once on the Edit Resource page you will see the base calendar in the Assignment Attributes section.

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS