Schedule: Changing finish date but the start date remains the same RRS feed

  • Question

  • Hi 

    I've gone through other questions on this, but to confirm is it possible that when the user changes the finish date on a task, that the start date remains the same but the duration changes?  And if so, how would you enable this on the schedule in the POL browser?

    FYI - This is something specific to a user's needs

    Many thanks 

    James 





    • Edited by JamesP435 Tuesday, July 11, 2017 10:36 AM
    Tuesday, July 11, 2017 10:22 AM

Answers

All replies