Project Server 2013 Timesheet for next period. RRS feed

  • Question

  • Dear Project users,

    If I have a task with planned hours for a specific week, and dont add any actual hours.

    Will PS transfer hours to next week and how?
    Or will it just leave them.

    I got mixed results so I am confused.

    With best regards,
    PEtar

    Monday, May 22, 2017 2:13 PM

Answers

  • Hi Petar,

    Project will NOT push any work to subsequent periods. This is up to the project manager to review his project plan, check for any remaining work and reschedule it after the status date.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    • Marked as answer by PetarB Monday, May 22, 2017 5:58 PM
    Monday, May 22, 2017 2:38 PM