none
Timesheet Manager not valid RRS feed

  • Question

  • Hi,

    In PWA 2007, I want to select a new Timesheet Manager for a resource, but I don't find it in the list of the Pick Resource dialog. What are the permissions I have to give to that user so that he may be a Timesheet Manager?

    Thnaks

    Sunday, October 17, 2010 2:36 PM

Answers

  • Generally, that person needs to be in the resource manager security group. That should be sufficient. There is a specific permission of "accept timesheets" which needs to be set if you are creating your own security group. There is a separate permission of "approve timesheets" which is likely to be required if the person is supposed to approve the timesheet rather than just review.
    Jack Dahlgren blogs at:
    Project and Retrovention
    and rarely Twitter
    • Marked as answer by WLID1966 Sunday, October 17, 2010 5:15 PM
    Sunday, October 17, 2010 2:41 PM
    Moderator