Calculating resources RRS feed

  • Question

  • Hi

    I will be using two cranes on site both identical. I have a similar situation with welding machines i.e. one task can use 4 welding machines and four welders.

    How can I add more than one of the same resource without giving it another name?

    I don't want 400t Crane 1 & Crane 2 And similarly I don't want Welder 1 & Welder 2..... Welder 20.

    I would like Project to tell me how many of the resources I need in total when I have scheduled say 2 or more to one task.

    Wednesday, April 4, 2012 10:24 AM