Allowing employees limited read/write capabilites RRS feed

  • Question

  • I want my employees just to update the % complete on the schedules. Everything else is read only capabilities. How do I do that?
    Thursday, December 5, 2013 3:29 PM

All replies

  • Hi Carrie

    In your PWA Site, click on Server Settings>> Under Time and Task Management>> Task Settings & Display.

    On 'Task Settings & Display' page, you will get an option under 'Tracking Method' section, from where you can make your employees (Team Members) just to update %Complete on their schedule.

    Hope this is the thing, you were looking for.

    Thanks


    Manish

    Friday, December 6, 2013 11:31 AM
  • Carrie,

    • Since you are using Project Online, we will need to know if you are using SharePoint Mode permissions or Project Server permission mo
    • Assuming you are using Project Server Mode permissions, you can adjust the Security Category and group permissions to make this happen.
    • And finally, Manish's suggestion below allows you to set % complete as a the tracking method.

    Please let us know, and we can try to hep you with a step by step.


    Prasanna Adavi,PMP,MCTS,MCITP,MCT http://thinkepm.blogspot.com

    Sunday, December 8, 2013 5:18 PM