none
Show Finish dates only on calendar RRS feed

  • Question

  • So it is easy to simply click on the calendar view and then use all sorts of filters to see my project's tasks.  But it shows the entire task duration as a blue bar on the calendar.

    What I would like to do it see only the finish date (or due date) on the calendar view.  I have been playing around with Project and searching the Internet and so far cannot figure out how to do this.

    Is it possible?  If so, please describe how I can do this.  

    TIA,

    RKS


    Robert Shields

    Tuesday, May 24, 2016 4:35 PM

All replies

  • RKS,

    First, sorry for the late response. The forum had problems for several days wherein new posts were not appearing. The issue is now fixed.

    Sorry but Project has very limited formatting options in the Calendar view. The only option I can suggest is to create a custom Gantt Chart view with each task marked as a milestone. That will show a finish milestone instead of the full Gantt Bar. Then set the Gantt Chart graphic to more closely resemble the Calendar view (see screen shot).

    It's not exactly what you want, but maybe it's close enough.

    John


    Saturday, May 28, 2016 3:22 PM