How to Change a Contour for Cost Type Resource

    Question

  • Hi, there,

    I am trying to change the contour of a cost type resource-in my case, it is construction contract executing for multiple years--to bell shape. However, all the articles online only mentioned change the work contour for work type of resource, such as man hours. Is there any way that I could change the load contour for cost resource? 

    Thanks,

    Elaine

    Wednesday, April 24, 2019 4:36 PM

Answers

  • Elaine,

    You can set the contour of a Cost type resource manually via one of the Usage views or you can do it with VBA but as far as I can tell there is no "contour button" for Cost type resources like there is for Work type resources.

    Hope this helps.

    John

    Wednesday, April 24, 2019 5:03 PM