Ms Project Status Date Split Problem RRS feed

  • Question

  • Hello,

    I have an scheduling problem in Ms Project.

    I have 3 activities a,b and c.  Activities a,b and c are link with FS respectively.

    When I rescheduled the project, started works split and remaning parts go after the status date.

    Since activity b has started and should continue by status date, only activity a start with status date and remaining part of b starts after activity a. 

    However, I want  the remaning part of b to be started by status date.

    How can I solve this problem? 

    Need your helps..

    Thanks..

    Friday, November 2, 2012 8:31 AM

All replies

  • Hi,

    Unlink the tasks by all means. The links cannot be real since b has started before a was finished. Introducing phony links will lead to phony results :-(

    Why can't the three tasks happen in parallel? If resource availability is the problem, better use resource leveling.

    Greetings,

    Friday, November 2, 2012 9:20 AM
    Moderator