Actual Work Hours Split from Multiple Resources on a Single Task RRS feed

  • Question

  • We have recently started using Project Online Timesheets in order to capture actual hours submitted by resources. I have a few tasks in my schedule with more than one resource assigned. Where can I view the breakdown of hours per resource? When I view the schedule in Microsoft Project, I obviously see the column for 'Actual Work' and I know this figure is the total hours submitted by resources assigned. However, I'm interested to know the split of hours per resource. I can't figure out where I can view this in MS Project, nor am I seeing an option in Project Online. 

    Any assistance is greatly appreciated! Would also be interested to know how everyone else is managing tasks with multiple resources assigned. Thanks!

    Monday, August 20, 2018 3:14 PM

Answers

  • Hi,

    please apply a usage view in MS Project, either Task Usage or Resource Usage.

    In Project Online, you can select an assignment view from dropdown in ribbon, e.g. Assignment Work.

    Does that show what you are looking for?

    Barbara

    • Marked as answer by KatieD_IA Monday, August 20, 2018 4:26 PM
    Monday, August 20, 2018 4:09 PM
    Moderator

All replies

  • Hi,

    please apply a usage view in MS Project, either Task Usage or Resource Usage.

    In Project Online, you can select an assignment view from dropdown in ribbon, e.g. Assignment Work.

    Does that show what you are looking for?

    Barbara

    • Marked as answer by KatieD_IA Monday, August 20, 2018 4:26 PM
    Monday, August 20, 2018 4:09 PM
    Moderator
  • The Task Usage option in MS Project shows what I was looking for. Thank you!

    Monday, August 20, 2018 4:30 PM