Create a report that shows costs / resource / summary task / month RRS feed

  • Question

  • Hi,

    I have a project plan with a single resource (with a rate added to resource sheet) that is assigned to a bunch of different tasks over a 4 month duration.

    I am trying to figure out how to create a report that shows the cost per month against each summary task. Can I do this?

    Can this be done?

    Thanks,.

    Byron

    Wednesday, December 13, 2017 6:16 PM

Answers

All replies

  • Byron,

    Sure, take a look at the Task Usage view and set the timescale to show months.

    Hope this helps

    John

    Wednesday, December 13, 2017 7:37 PM
  • John, that provides the summary hours per month, do you know how to flip those hours into costs? I.e. each of the tasks has a resource with a rate assigned to it so the costing column on the left side of the chart is filled in, I would those costs broken down by month.
    Wednesday, December 13, 2017 8:40 PM
  • On the grid, not the table, right click and select cost (and other useful things too)

    Any help?

    Wednesday, December 13, 2017 10:00 PM
  • WOOT! THanks Trevor (and John) - this is exactly what I was looking for.

    Byron

    Thursday, December 14, 2017 8:35 PM
  • Byron,

    You're welcome and thanks for the feedback.

    John

    Thursday, December 14, 2017 8:46 PM