Labelling the Baselines 1 to 10 in MS Project 2010 RRS feed

  • Question

  • Is there any way to change the Baseline references in MS Project 2010 ?

    I would like to globally change say Baseline 1 to be 'Baseline at PG1' etc.

    Many thanks,

    Mick

    Bristol, England. UK 

    Tuesday, February 12, 2013 7:50 AM

All replies

  • Hello Mick,

    You can rename columns, so you could rename each of the "Baseline 1" columns (start, finish, duration, effort), and that will help somewhat.

    However, that won't rename the baselines themselves, so when you go to set the baseline, you'll still be looking at "Baseline 1". There's no way of renaming the actual baseline names.

    An old school solution - like printing out a list of what baselines are used for which purpose and sticking it somewhere, may be the best idea. Or just a word doc with the mapping that people can access.

    Thanks,
    Andrew


    Tuesday, February 12, 2013 9:27 AM