  • Hi,

    Using Project Server2010 and MSP Professional 2010.

    In Project Server, is there a way to find and use for reporting the UniqueID that is generated when creating a task in Project Professional?

    No problem in selecting tasks from the reporting database and returning Enterprise fields, but have also been asked to include in the report the UniqueID as attributed when craeting tasks in Project Professional.

    Thanks

    Thursday, September 6, 2012 11:54 AM

Answers

  • I think TaskClientUniqueId from the table dbo.MSP_EpmTask in the reporting database is what you are looking for.

    Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com

    Thursday, September 6, 2012 1:17 PM
    Moderator
  • Hi,

    this field is also available in MSP_EpmTask_UserView.

    Regards
    Barbara

    • Marked as answer by Mathonex Thursday, September 6, 2012 1:26 PM
    Thursday, September 6, 2012 1:18 PM
    Moderator

All replies

  • I think TaskClientUniqueId from the table dbo.MSP_EpmTask in the reporting database is what you are looking for.

    Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com

    Thursday, September 6, 2012 1:17 PM
    Moderator
  • Hi,

    this field is also available in MSP_EpmTask_UserView.

    Regards
    Barbara

    • Marked as answer by Mathonex Thursday, September 6, 2012 1:26 PM
    Thursday, September 6, 2012 1:18 PM
    Moderator
  • Thanks to you both - brilliant -  don't know how we had missed that!
    Thursday, September 6, 2012 1:26 PM