MS Project 2013 - Inactive Tasks showing in Reports RRS feed

  • Question

  • Hello,

    I am wondering why tasks that have been inactivated in the project are showing up in the project reports? For example, when I look at the 'Late Tasks' report, I have multiple inactive tasks that are showing up as late. 

    Is this a bug? 

    Cheers, 
    Michelle

    Tuesday, May 26, 2015 4:20 PM

Answers

  • I am seeing the same thing.  As a work around, create a copy of the Late Tasks and add a second line as an AND condition:

    Field: Active

    Test: Equals

    Value: Yes

    That will only show late tasks that are active.  You can apply that filter to the Late Tasks report instead of the standard Late Tasks filter.

    I hope this helps.


    Tuesday, May 26, 2015 4:50 PM
    Moderator

All replies

  • I am seeing the same thing.  As a work around, create a copy of the Late Tasks and add a second line as an AND condition:

    Field: Active

    Test: Equals

    Value: Yes

    That will only show late tasks that are active.  You can apply that filter to the Late Tasks report instead of the standard Late Tasks filter.

    I hope this helps.


    Tuesday, May 26, 2015 4:50 PM
    Moderator
  • Thank you so much Julie! :)
    Tuesday, May 26, 2015 9:14 PM
  • You're welcome, Michelle and thanks for the feedback.
    Tuesday, May 26, 2015 9:38 PM
    Moderator
  • When you click on the Late report the field list shows on the right of your screen. You should find that the Filter is showing "Late Tasks". Change this to "Late Tasks (Active)" 
    Tuesday, February 9, 2016 8:40 AM