Task Percent Complete RRS feed

  • Question

  • There are two resources assigned in one task.

    Resource A [50%] & Resource B [50%]

    Resource A has completed his task, sent for approval and accepted.

    How Resource B could see the Task is 50% completed?

    Is there any field that can show Task progress/% Complete in Assignment view column?

    OR

    Is this possible that remaining 50% Task will appear in Resource B's tray when Resource A will complete his 100%?

    Regards,


    Noman Sohail

    Wednesday, September 30, 2015 10:44 AM

All replies

  • Yes the field is %Complete (Task).

    Simply add % Complete (task) to My tasks view in Project Server/Online administration interface.

    Best Regards | Power2Plan | https://www.power2plan.com

    Wednesday, September 30, 2015 2:00 PM
  • Thanks John,

    Yes, in Project views, it shows overall Task progress (in %Complete) from both resources

    BUT

    %Complete field in My Work (My Assignments view) shows Resource B's Task progress only - not overall Task progress.

    I need overall Task progress (%Complete or any other) in My Work (My Assignments view).

    Regards,


    Noman Sohail


    • Edited by NomanSohail Thursday, October 1, 2015 5:10 AM Update
    Thursday, October 1, 2015 5:10 AM