  • Question

  • I have earned method selected for the entire project as % complete, however all the individual task's are being calculated by physical % complete....When I double click an individual task, it shows % complete as the earned value method....any suggestions?
    Thursday, November 10, 2011 7:50 PM

Answers

  • NicholasB14 --

    Apply any task view, such as the Gantt Chart view.  Right-click on the Duration column header, select the Insert Column item, and select the Earned Value Method field.  In the Earned Value Method field for the first task, select the % Complete item and press the Enter key.  Select the changed cell and then use the Fill Handle to fill the new value down to every other task in the project.  Hope this helps.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Thursday, November 10, 2011 11:57 PM