Baseline 3 Remaining work in MSP 2010 - Is this available? RRS feed

  • Question

  • I need this for monthly finance stuff as i forgot to archive at the correct time so..Baseline 3 Remaining work in MSP 2010 -  Is this available?

    Friday, March 1, 2013 2:19 AM

All replies

  • GraemeButt --

    Nope, there is no such field as Baseline 3 Remaining Work.  There is a Baseline 3 Work field, however, if that makes a difference.  Hope this helps.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Friday, March 1, 2013 3:11 AM
    Moderator
  • Graeme, to repeat Dale's answer, nope. None of the Baseline field sets include a Baseline Remaining Work field. There are Variance fields which, by default, are calculated against the Baseline (0) data - although you can select Earned Value calculation against a different Baseline under the File->Options->Advanced selection.

    Your best bet would probably be to set up a custom task number field with a formula to calculate your information as [Baseline3 Work] - [Actual Work]. If you needed this at the assignment level, I think it would need some code.

    Graham

    Friday, March 1, 2013 6:29 PM