none
2013 - comparison report not picking up task or date changes RRS feed

  • Question

  • Task Table = Entry

    Resource Table = None (only need to see task and date changes)

    I can see the differences in the dates as they are side by side but the Task Mode: Diff column shows Equal. Shouldn't it show Different where ever there is a change?

    Thursday, July 20, 2017 4:31 PM

All replies

  • proyecto123 --

    Task Mode refers to whether a task is Manually Scheduled or Auto Scheduled.  If the Task Mode value is the same for a task in both projects, the Task Mode: Diff column will show Equal.  The column has nothing to do with date changes.  Hope this helps.


    Dale A. Howard [MVP]

    Thursday, July 20, 2017 4:44 PM
    Moderator