Update tasks as complete turns them to milestones RRS feed

  • Question

  • Hi,

    I'm using MSP Pro 2010 for my workplan. I manually update tasks with the 'Actual Finish' dates to sync them with a parallel tracking system. In doing so, some tasks are converted to zero duration since the work is truncated in the process. This makes MSP to think they are milestones & sets the milestone flag to 'Yes'. This is not what is required since it has implications in reporting. I have tried manually setting the flag back to 'No' but it doesn't seem to work on re-opening the workplan.

    Is there a way to update such tasks with actual finish dates & not convert them to milestones?

    Thanks

    Fabian

    Wednesday, August 22, 2012 8:05 AM