Project Restore - Project Server 2010 RRS feed

  • Question

  • Greetings!    

    We are in the need to restore a single project back into the enterprise from last night.    

    I understand that we will lose any changes to the project that have been made since the restore.   No issue there.   My question is related to any APPROVALS that may have been processed against tasks TODAY.     If we proceed with the project restore - will the approvals for those tasks be pushed BACK into the PM's approval queue?    If not - how are approvals handled when you restore a project?

    Thank you,

    Randy  K.

    Wednesday, August 5, 2015 8:00 PM

Answers

  • Randy,

    The approvals will NOT be pushed back to the Project Manager's queue, as a result of the restore. 

    One thing you could try is to have resources resubmit the changes. Alternatively, you could look at the update history and update the project manually. Since you are talking about just one project, this should be less risky.


    Cheers,

    Prasanna Adavi, Project MVP

    Blog:   Podcast:    Twitter:    LinkedIn:   

    Wednesday, August 5, 2015 10:20 PM