Quantity of Material Resource changed In visual report (also showing in decimal) RRS feed

  • Question

  • Respected All,

    Please i am facing problem in resource work summary visual report as i am not finding my allocated exact material resource quantity in my report (e.g in week 44 i have 300 SQM paint with 2days duration  but in reports its showing 85.33333) similar problem in other materials.

    Kind response is requested please.

    Sunday, November 11, 2012 3:08 AM

All replies

  • What does the resource quantity look like in week 45 (or 43)? Is it possible that the dates for the task have been shifted so that it spans part of Friday in week 44 and Monday and part of Tuesday in week 45?

    Graham