none
Can't edit % Completion as Project Lite User RRS feed

  • Question

  • Hi there! 

    I try to edit an activity that has been assign to this user, to update % completion for this task. 

    The edit bottom is grey out and it looks blocked. This is important so that my team can collaborate within this project, based on resource assignments.

    Any suggestions?? Thanks!



    • Edited by isa7667 Saturday, July 26, 2014 4:35 AM
    Saturday, July 26, 2014 4:33 AM

Answers

  • Hi,

    From your screenshot, I can see that you are directly in the project plan. As a team member, you cannot edit the project plan directly, either from Project Lite, Project Online or on premises.

    The project manager (project owner) has to create assignments, publish them to team member which will go to the task update (or timesheet in case the Single Entry Mode is activated) to enter actual/completion. Then the project manager will approve or reject those updates which will update the project plan accordingly.

    This is the process.


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    • Marked as answer by isa7667 Sunday, July 27, 2014 8:50 PM
    Saturday, July 26, 2014 12:23 PM
    Moderator