none
Question about the rates in EPM 2007 & the contract value RRS feed

  • Question

  •  

    I Have couple of questions here about EPM 2007 , first I have request from the top management to hide the employees rate is there any possible way to do this ?

    My other question about the contract value , can I compare the contract value with the actual cost ?

    Tuesday, February 12, 2013 10:17 PM

All replies

  • Hi,

    You can modify Views from Server Settings. Is Contract value is a CF? and do you mean showing the different of the two? Please elaborate.


    IN
    Thanks, Kashif

    Wednesday, February 13, 2013 6:02 AM
  • Mosua --
     
    Although you can hide resource cost rates in PWA views, you CANNOT hide them from your project managers in the Resource Sheet view in Microsoft Project 2007.
     
    Regarding contract value, where are you storing this information in the project?  Is that what you see in the Cost column?  And di you save a Baseline for your project?  If so, apply any task view, such as the Gantt Chart view, and then click View > Table > Cost.  In the Cost table, examine the data shown in the Cost Variance column.  This column shows the difference between the current Cost value and the original Baseline Cost value for every task.
     
    Let us know and we will try to help.

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Wednesday, February 13, 2013 1:56 PM
    Moderator
  • Thanks for reply for the second questions my idea was about the total contract value is there any way to compare it with the budget in order to calculate my revenue?

    Wednesday, February 13, 2013 2:16 PM
  • Mousa --
     
    Please understand that we want to help you, but we need to know exactly where you store the total contract value for your project.  Are you using a custom Cost field for tasks?  Are you using a Budget Cost resource?  We need to know where you are entering the total contract value before we can answer your second question.  Please let us know and we will try to help you.
     

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Wednesday, February 13, 2013 7:02 PM
    Moderator